Update from Jessups

Posted on: 12 May 23

We’ve received the following update from Jessups regarding the overflow car park. If you have any further queries please contact us on [email protected]

Stage 1 works – Work started on Tuesday 9th May to a chamber in the highway in front of the contractor’s car parking area. For these works to happen the contractors have to park on one side of the pavement around the development and we will keep the other pavement clear to allow the pedestrians free and unobstructed movement.

Stage 2 works – Starting school half term w/c 29-5-2023 – removing all tarmac and stone from both car parks and forming a temp car park for the use of the school overflow only. This will stay in place until the car park at the Croppings is available.

Stage 3 works – Starting WC 5-6-2023
The phase and road will not be accessible to the public and will be closed off with Heras fences and gates.