Update from Keepmoat - The Paddocks

Posted on: 24 May 23

Further to recent communication below is an update on the works to the roads on the estate we are programming to carry out over coming weeks. 

•         Over the coming weeks works we will continue to work on highway area to raise ironworks, carry out kerb remedials and reinstate road build ups where needed across the estate roads including Crystal Drive, Monksmoor Road, New Meadow Drive. 

Next stages for surfacing:

•         Crystal Drive – Road binder course commence 19th June followed by surface course commence 26th June.

•         Monksmoor Road (o/side no.17 up to no.65) – Road binder course commence 20th June followed by surface course commence 27th June. 

•         New Meadow Drive (o.side no.53 down to no. 31) as above.

•         New Meadow Drive (o/side no.29/31 down to entrance) – Road binder course commence 21st June followed by surface course commence 28th June.

•         Entrance area New Meadow Drive / The Bache – Road binder course commence 22nd June followed by surface course commence 29th June.

Our sub-contractors will continue to liaise with residents in the areas affected and maintain traffic management systems on site to facilitate works. The final stages following surfacing works will be to carry out Highway inspections, de-mobilisation of compound and reinstatement of POS area and planting as required.

We thank you for your ongoing co-operation during these works. If you have any queries relating to this information, please contact us via [email protected]

Notes:

  1. Road binder course/surface cause is the build-up of layers for the road construction below the final surfacing course.
  2. Sub-contractors are Conro & Sons and they will letter drop in areas they are working.
  3. The traffic management system will vary depending on the type of work, for some areas the machinery is larger and so may have to part close sections of road/half width carriageways, it will be suited to the operation in hand.