Highways Adoption Works – Lightmoor Way
Posted on: 25 Sep 25
Telford and Wrekin Council will shortly be commencing work on behalf of Bournville Village Trust as part of the highways adoption process.
They will be:
• Shortly carrying out footway & carriageway improvement works on Lightmoor Way.
• Works include: streetlighting, kerbing, block paving, ironworks, footway surfacing, and carriageway resurfacing.
• Works will be completed by Balfour Beatty and specialist sub-contractors MSM, Tarmac and Quantum Traffic Management
When is this work being completed?
Footway Improvements
The work is due to take place on 01/10/2025 and be completed by 19/12/2025 (weekdays only) weather permitting. Please see below the phased traffic management for these works:
- Phase 1 (01/10/2025-17/10/2025) – 24hr road closure from the A4169 mini roundabout to Little Flint.
- Phase 2 (20/10/2025-24/10/2025) – 24hr road closure on Lightmoor Way (From Furnace Avenue heading towards Little Flint) with 2-way traffic lights on Furnace Avenue
- Phase 3 (27/10/2025-19/12/2025) – 24hr road closure from A4169 mini roundabout to Furnace Avenue
Carriageway Improvements
The carriageway resurfacing works are estimated to be completed around March 2026, more details will be released closer to the start date. This will include resurfacing on both access roads to Lightmoor Village from the North and South.
Balfour Beatty will be the lead delivering this work in partnership with the Council and contact details are below. Pleaes contact them for any questions or queries.